Charlotte-Raleigh
North America Data Center Trends H1 2025
2025 年 09 月 08 日 4 分鐘 閱讀
Colocation Insights
- American Tower delivered 1 MW of capacity at a Raleigh cell tower site.
- Developers with existing land positions are working to secure tenants even though power deliveries won’t occur until mid-2027.
Market Trends
- Duke Energy is requiring end users to sign power commitments and increase capital contributions, making it more difficult for developers to conduct business.
- With power generation near Charlotte seemingly at capacity, some developers are delaying new projects or shifting to alternative uses for sites.
- Sites at the perimeter of Duke Energy’s service territory, outside of the clustered area near Charlotte and along I-85, may be some of the last near-term opportunities for development in the Carolinas.
Notable Activity
- Enovum Data Centers acquired a 1 million-sq. ft. building for conversion to a data center in Madison, NC.
- Cielo Infrastructure announced a new 1.6 million-sq.-ft. data center campus in Gaffney, SC.
- AWS announced a $10 billion total buildout investment on 800 acres in Hamlet, NC.